The Nelson County Board of Zoning Appeals denied on December 3, by a 3-2 vote, four of Dominion Energy’s applications for the variances to the County’s flood plain ordinance needed to construct the Atlantic Coast Pipeline across flood plains in Nelson. The other seven of the original eleven applications were dismissed in January 2018, and ACP will have to submit new applications for them.

The Nelson County Zoning Ordinance specifically includes “Structures or facilities that produce, use, store, or transport highly volatile, flammable, explosive, toxic, and/or water-reactive materials” in the list of “critical facilities [that] are prohibited from being constructed or operated within a SFHA [Special Floodplain Hazard Area] unless a Variance is granted.”

For more, see the Friends of Nelson County press release.